Connect with us

Energy & Infrastructure

Tesla Unveils Powercore Solid-State Power Platform Aimed at Grid Bottlenecks and AI Data Centres

Tesla has introduced Powercore, a 7.4 MW unit that combines a transformer, inverter and circuit breaker in one enclosure. It targets long equipment lead times in storage, solar and data-centre projects, but Tesla has not disclosed a price, size or launch customer.

Published

on

Tesla Unveils Powercore Solid-State Power Platform Aimed at Grid Bottlenecks and AI Data Centres

Tesla has unveiled Powercore, a solid-state medium-voltage unit that combines a transformer, an inverter and a circuit breaker in one enclosure, aimed at data centres, large solar farms and its own Megapack storage sites. The company announced it on 17 November 2026 through its Megapack account on X.

The unit is rated for 7.4 megawatts (MW), or 9 megavolt-amperes (MVA), continuously at 34.5 kilovolts AC, with grid-forming support for 10 MVA of peak power. Tesla claims a peak efficiency of 98.86 percent. The company says it will be made in America and operating in 2027. Electrek reported that the unit will be built in the US “of U.S. and imported parts.”

Conventional installations need separate inverters, transformers and breakers. Powercore replaces the large iron-and-copper transformer with fast-switching power electronics. Tesla says the unit includes the industry’s first built-in solid-state circuit breaker, which can clear electrical faults in 100 microseconds. The company puts that at roughly 1,000 times faster than traditional mechanical breakers. Tesla also says the design removes the flammable insulating oil used in classic transformers, operates from minus 40 to plus 55 degrees Celsius, and carries a warranty of up to 25 years.

The data-centre case is central to the launch. According to pv magazine USA, it is designed to take grid power from the feeder and deliver 800-volt DC to servers in a single step. That matches a shift led by Nvidia, which said in May 2025 that it would move to 800-volt direct-current power to support 1-megawatt server racks, with full-scale production of such data centres in 2027. Tesla also markets the unit for 1,500 to 2,000 volt DC solar sites and off-grid data centres.

Timing matters because equipment is scarce. Electrek notes that lead times on conventional transformers are stretching into years as data centres and renewable projects pile into interconnection queues. Tesla says it can build Powercore in factories that already produce power electronics for its vehicles and Megapack batteries.

Important details are missing. Tesla did not give a price, the unit’s size or weight, or a launch customer. Electrek reported that Tesla has not shared a factory location. The efficiency, fault-clearing and uptime figures are the company’s own claims, and no independent testing has been published.

Tesla is not the first to market. Heron Power, founded by former Tesla senior vice president Drew Baglino, announced that it has raised $140 million to build gigawatts’ worth of solid-state transformers for data centres and the grid. Heron also plans volume production in 2027 and has named customers, including Intersect and RWE. At about 5 MW for solar and storage and about 4.2 MW for data centres, its Heron Link is smaller per unit than Powercore.

Business Diary Analysis

Powercore is a bet that integrating several grid components into one factory-built product can beat the queue for custom equipment. If Tesla delivers on its claims, project developers could save on site work and component sourcing, while Tesla gains a product that ties together its Megapack batteries, solar and data-centre business. The company has said it already has 10 GWh of Megapack running at data centres.

The unknowns are commercial. Without a price, a factory location or a customer, Powercore remains an announcement, and the 2027 date means Tesla and Heron will reach the market together. Solid-state transformers have been in development for more than a decade, and large-scale reliability and cost parity with conventional units are still to be shown in service.

For Zimbabwe, the direct relevance is limited for now. Powercore is a utility-scale product made in the US, and Tesla has said nothing on pricing or export availability. Its significance is as an indicator of where grid equipment is heading. Zimbabwean developers of solar, storage and mining power projects have had to plan around long equipment lead times and import costs, so power-electronics products that cut component count and site work could in time become relevant to them. That is our assessment, not a Tesla claim, and it depends on pricing, service support and availability in the region.

What’s Next?

Watch for pricing, a factory location and named customers. Independent testing and the first 2027 installations will show whether Powercore performs as claimed. Competing launches from Heron and others will show how quickly solid-state transformers enter the mainstream.

Sources

The Business Diary magazine is a comprehensive publication that centers around business and economic development news. It covers a wide range of topics including finance, mining, technology, environment, climate finance, and agriculture. With its focus on providing valuable insights and updates, the magazine caters to readers who are interested in staying informed about the latest developments and trends in the business and economic landscape of Zimbabwe.

Continue Reading

Energy & Infrastructure

Mutapa Fund Pushes Zimbabwe Towards Regional Fuel Hub

The Mutapa Investment Fund, which controls the National Oil Infrastructure Company (NOIC), wants Zimbabwe to move from importing fuel for itself to handling it for its landlocked neighbours. Pipeline expansion is already under way, with capacity set to rise from 3 billion to 5 billion litres a year by the end of 2027. The plan’s value will depend on cost, financing, pricing and competing routes, none of which is fully public.

Published

on

Mutapa Fund Pushes Zimbabwe Towards Regional Fuel Hub

Mutapa Investment Fund chief executive Dr John Mangudya said at a public lecture this year that NOIC’s fuel handling capacity is being raised from 3 billion to 5 billion litres a year. Zimbabwe, he said, aims to become a regional fuel hub using its location and pipeline infrastructure, with Zambia, Botswana and Malawi as target markets.

On 3 September, Presidents Emmerson Mnangagwa and Daniel Chapo announced the expansion of the Beira–Harare fuel corridor. Mozambique’s CPMZ pipeline is to rise 67%, from 3 million to 5 million cubic metres a year, which equals an extra 2 billion litres annually. Completion is targeted for the end of 2027.

Background

NOIC is a Mutapa subsidiary. The Mutapa Investment Fund manages a portfolio of about US$16 billion and more than 30 State-owned enterprises. The Feruka pipeline, which runs between Harare and Beira in Mozambique, carries most of Zimbabwe’s fuel imports. The Herald put the share above three-quarters. An Afreximbank-related report put it at about 85%.

A 2024 upgrade raised the CPMZ pipeline’s capacity from 2 million to 3 million cubic metres a year. NewsDay reported in May that NOIC plans a US$400 million second phase to reach 5 billion litres by the end of 2027.

Demand is growing. The Herald reported diesel consumption of 1.04 billion litres in 2022, 1.07 billion in 2023 and 1.12 billion in 2024, with total fuel consumption up nearly 30% in the 11 months to November 2024. It attributed the demand mainly to mining, including lithium and platinum, transport and agriculture. Those figures are now almost two years old.

Key developments

  • Pipeline expansion: new pumping stations at Nhamatanda and Messica in Mozambique, coordinated with a planned expansion of the Petrozim Line between Feruka and Harare. Work is to proceed without disrupting current supply.
  • Longer-term options: a larger-diameter line of about 12 million cubic metres a year, aimed at meeting regional demand through 2050, and a possible extension of the Harare–Lusaka route into Zambia’s Copperbelt.
  • Financing: Afreximbank is reported to be in talks with the Mutapa fund and private firms to expand the Beira–Msasa pipeline and extend it to Zambia. Zimbabwe’s annual fuel bill is cited at US$1.86 billion.
  • Beneficiaries: Mozambique, Zimbabwe, Zambia, Malawi, Botswana and the DRC.

CPMZ chairman António Laice said the project “adds substantial capacity to one of the region’s most important fuel routes.” Mnangagwa said it “will support Zimbabwe’s energy security.”

What it means for the economy

Costs and the external balance. More pipeline capacity can lower transport costs by reducing reliance on road tankers. The Herald said NOIC’s expansion aims to meet demand, cut import costs and strengthen strategic reserves. Savings depend on actual tariffs and prices, which are unpublished.

Mining and industry. Mining is among the main drivers of fuel demand, so dependable supply matters to producers.

Transit revenue and regional trade. A hub could earn fees from fuel moving to neighbours. The size of that market has not been published, and neighbours have other supply options.

Competition. Afreximbank is working with Dangote Refinery on a tank farm at Walvis Bay in Namibia. It says Zimbabwe, Zambia and Botswana could receive fuel from Lagos within five days. Analyst Walter Mandeya of Trigrams Investments said landed fuel prices could fall 15–20% within 18 months if the Walvis Bay tank farm is delivered. That is one analyst’s estimate. If it proves right, it would compete with the Beira route.

Risks. Heavy dependence on one corridor is itself a supply risk. The capacity increase also needs financing and delivery on time. And a regional hub depends on prices that neighbouring buyers find attractive.

Our Analysis

Zimbabwe’s geography gives it a credible claim to be a transit point, and the pipeline work shows the plan is more than rhetoric. But a hub is a commercial proposition, not a title. It succeeds when fuel arrives reliably, costs less than alternatives and is priced competitively for buyers in Zambia, Botswana and Malawi. Readers should watch for published tariffs, financing terms and signed supply agreements with neighbours.

What’s next?

Watch for the financing structure of the US$400 million expansion, construction progress on the pumping stations and the Petrozim Line, signed supply agreements with neighbouring countries, and published pipeline tariffs.

Continue Reading

Energy & Infrastructure

Harare’s 7.4MW Rooftop Solar Project Nears Commissioning and Tests Zimbabwe’s Power Wheeling Framework

A 7.4MW rooftop solar installation at Willowvale in Harare is close to commissioning. It will deliver power to an industrial customer through the national grid, under Zimbabwe’s wheeling framework. That makes it an early test of whether businesses can buy electricity from private generators away from their own premises. Many details, including cost and the customer, have not been disclosed.

Published

on

Harare’s 7.4MW Rooftop Solar Project Nears Commissioning and Tests Zimbabwe’s Power Wheeling Framework

Limpopo Way Power’s 7.4MW rooftop solar project at the Willowvale Industrial Site in Harare is nearing commissioning, according to a report published on 8 November 2026 by GreentechLead. The panels cover about 33,500 square metres across two warehouses. A 7.2-kilometre, 33-kilovolt line will connect the plant to the Kambuzuma substation.

The power will go to an unnamed industrial customer under Zimbabwe’s electricity wheeling framework. The report says delivery is “subject to final testing and approvals”. No commissioning date was given. The investment amount, the customer and the commercial terms are undisclosed, and the report carried no quotes from the developer, the customer or officials.

What wheeling means

Wheeling lets a generator send electricity to a customer at a different location by using the grid, usually in exchange for a fee to the grid owner. For a business, it means buying solar power from a plant that is not on its own roof. This matters in a country where factories and mines have faced unreliable supply.

Background

Zimbabwe has been moving towards private and captive generation. Mining Zimbabwe reported in March 2026 that new Own-Consumption Licensing Regulations legalise captive power and set licensing procedures and minimum installation standards. It also reported Energy Management Regulations requiring monitoring and reporting of consumption, and Backbone Infrastructure Provision Regulations inviting private investment in high-voltage transmission. The same report said unreliable national supply and load-shedding were pushing mines towards self-generation, and that Zimplats is targeting 185MW of self-generation. The Zimbabwe Energy Regulatory Authority enforces the rules.

What it means

Industry. A 7.4MW supply can cover a meaningful part of a large factory’s daytime demand. If the wheeling arrangement works and is affordable, other manufacturers and commercial users could copy the model without building their own plants.

Developers and investors. The project is a precedent for how long approvals take, what wheeling costs and how contracts are structured. Clear answers would encourage more rooftop and ground-mounted projects. Unclear or costly terms would discourage them.

The grid and the utility. Wheeling uses the existing network. Its effect depends on the charges, the technical conditions and how the arrangement affects the utility’s revenue and grid stability. None of these details has been published.

Mining and the wider economy. Mining is among the largest users of power, so a working wheeling model could matter beyond Harare. For scale, the Zimplats solar plant at Selous is 35MW. The Willowvale project is a fifth of that size but sits on existing roofs and sells to a third party.

Risks. The main ones are failure to secure final approvals, unattractive wheeling charges, grid constraints and, for any solar plant, the fact that it generates mainly in daylight and does not remove the need for night-time supply.

Business Diary Analysis

The importance of this project lies less in its 7.4MW than in what it tests. If the regulator, utility and developer can make a wheeling deal work in Harare, the model could spread. If approvals drag or charges erode the savings, the framework will look better on paper than in practice. Businesses weighing similar arrangements should watch the published terms, not just the headline capacity.

What’s next?

Watch for final approvals and commissioning, the publication of wheeling charges and contract terms, the customer’s identity, and whether other developers announce similar projects.

Continue Reading

Energy & Infrastructure

Zimbabwe Gazettes Invictus Energy’s Cabora Bassa Gas Deal: What It Means for the Economy

Zimbabwe has formally published its production sharing agreement with Invictus Energy for the Cabora Bassa gas project, completing a deal signed in May. The agreement gives investors legal certainty. Any benefit to the economy depends on what drilling finds and whether the gas can be financed, processed and sold.

Published

on

Zimbabwe Gazettes Invictus Energy’s Cabora Bassa Gas Deal: What It Means for the Economy

The Government Gazette published the agreement on Friday 30 October 2026 as General Notice 2101 of 2026. Invictus announced it on 2 November. Gazettal completes the formal steps for the petroleum production sharing agreement (PPSA), which was signed in Harare on 27 May. Finance Minister Mthuli Ncube and Mines Minister Polite Kambamura attended the ceremony. The parties are the Government, Invictus as operator, and Geo Associates (Pvt) Ltd, the license holder, which is 80% owned by Invictus.

Invictus managing director Scott Macmillan called the signing “finally done” and a “model contract for future agreements”. Ncube called the project “a strategic national undertaking with the potential to reshape Zimbabwe’s economic landscape” and said it could reduce petroleum import dependence.

What the deal provides

  • A long-term fiscal, legal and commercial framework for exploration, appraisal, development and production in the Cabora Bassa Basin, a 360,000-hectare area in northern Zimbabwe.
  • A government share of benefits through production and profit sharing, plus royalties and corporate tax. The Mutapa Investment Fund’s participation is also formalised.
  • National Project Status and Special Economic Zone status, described as providing contract stability and investment protection.
  • Rules on the environment, decommissioning, local employment and local procurement.

Percentages, royalty rates, licence duration and cost-recovery terms have not been published yet.

The resource: promising, but not yet proven reserves

The Mukuyu gas-condensate discovery was ranked by Wood Mackenzie as Sub-Saharan Africa’s second-largest petroleum discovery of 2023. Estimates cited in local coverage run to as much as 20 trillion cubic feet of gas and 845 million barrels of condensate. The next well, Musuma-1, targets an unrisked mean prospective resource of 1.2 trillion cubic feet and 73 million barrels. Prospective resources are estimates of what might be found, not reserves, and drilling can disappoint.

Invictus says Musuma-1 is expected to spud in November 2026. It raised A$10 million in a placement to fund pre-drill work and the well.

What it could mean for the economy

Energy and power

Development economist Dr Eddie Mahembe said gas could become a third source of base-load electricity, since hydropower is less reliable and coal output is constrained by ageing infrastructure. Reliable power is a constraint on mining, manufacturing, farming and households alike.

Imports and the external balance

Ncube’s argument is that domestic gas and condensate could reduce spending on imported petroleum products. That would ease pressure on foreign currency. No figures have been published on import savings, gas prices or buyers, so the size of any effect is unknown.

Agriculture

Mahembe also pointed to possible nitrogen fertiliser production, which would matter for a country that imports much of its farm inputs. This is a possibility, not a plan.

Jobs and local business. The agreement includes local employment and procurement provisions, and Mahembe noted that construction before drilling could create activity. Employment numbers have not been published.

The risks

Mahembe flagged resource quality and depth, transport infrastructure, land and resettlement for rural residents, and unpublished environmental and compensation information. He called commercial viability “the central test.” Development costs, gas pricing and offtake arrangements have not been disclosed.

Business Diary Analysis

The gazettal removes a legal uncertainty that has held the project back for years. It does not remove the geological, financial or infrastructure risks. The sensible reading is that Zimbabwe now has a credible framework and an operator ready to drill. Whether that becomes power, fertiliser and export earnings will be decided by Musuma-1, appraisal results and financing over the next few years. Until then, claims about GDP uplift are premature, and the public deserves to see the fiscal terms.

Key takeaways

  • The Cabora Bassa PPSA was gazetted on 30 October 2026, completing the deal signed on 27 May.
  • Musuma-1 drilling is expected to start in November 2026 and will test a 1.2 trillion cubic feet prospect.
  • Possible gains are power supply, lower fuel imports and fertiliser. None has a published size or date.
  • The fiscal terms and the Government’s equity position are not fully public.

What’s next?

Watch for the Musuma-1 spud and results, Invictus’s appraisal plan for Mukuyu, financing and partner announcements, publication of the fiscal terms, and environmental and compensation disclosures.

Sources

Continue Reading

Trending

×