HARARE – PPC Limited is moving forward with plans for a new 1.5 million tonne a year integrated cement plant in Zimbabwe. The group’s Zimbabwean business is now contributing more than half of its earnings, and the company has told investors it wants to add clinker and cement capacity there. No capital cost, site or construction date has been published, and the project is still subject to board and external approvals.
What PPC has said
In its interim results for the six months to 30 September 2026, PPC listed a planned integrated cement plant in Zimbabwe of 1.5 million tonnes a year among its outlook items, alongside a 20 MW solar project with battery storage.
Management told analysts that Zimbabwe’s current demand of about 3 million tonnes a year leaves room for the plant. It also said its strategy is to improve local production in Zimbabwe rather than ship South African cement across the border.
In a September operating update, PPC said work on the project includes continued engagement with Sinoma on the engineering, procurement and construction (EPC) contract, mine prospecting, and an assessment of acceptable financing alternatives. Those are preparatory steps. A final investment decision has not been reported.
Background
The plant follows an agreement PPC signed earlier this year with China’s Sinoma Overseas Development. The memorandum covered efficiency improvements at PPC Zimbabwe and a feasibility assessment of a new integrated plant. PPC said then that any such investment would be assessed under its capital allocation framework and would need internal and external approval.
PPC has talked about expanding in Zimbabwe before. Global Cement reported plans for a US$200m clinker plant in the north-east of the country, with a feasibility study said to be almost complete. In 2015, the company said it was still looking for a reliable limestone source for a clinker plant. That project did not proceed as announced. The new plan comes after years of work to stabilise the existing operations.
PPC currently operates plants in Bulawayo and Harare with a combined annual capacity of 1.4 million tonnes and holds more than half of the market. Its Colleen Bawn plant produces clinker, the main ingredient in cement. A deputy minister has said PPC is the only local producer currently making clinker.
Earnings
The Zimbabwean business has become central to the group. Group EBITDA rose 23.7 per cent to ZAR1.216bn (US$71.7m) in the half year. In Zimbabwe, cement volumes rose 5.4 per cent, EBITDA rose 56 per cent to US$39m, and the margin widened from 23.4 to 31.5 per cent. By our calculation, Zimbabwe therefore supplied about 54 per cent of group EBITDA. By contrast, cement volumes in South Africa and Botswana fell 7.9 per cent.
PPC attributed the improvement partly to higher output of its own clinker and better plant performance, despite increased coal and diesel costs. The Zimbabwe margin was lower than the 34.2 per cent reported for the five months to August. PPC said a planned Colleen Bawn shutdown in September and October pulled it down. That shutdown was completed by mid-October.
For the year to March 2026, the Zimbabwean subsidiary paid a record US$36 million in dividends to its parent, up from US$13 million a year earlier.
Market conditions
PPC’s confidence comes after a turbulent period for the market. Zimbabwe introduced a 30 per cent surtax on imported cement in May 2025 through Statutory Instrument 50A of 2025 to support local producers. In November 2025, Harare lifted import controls and the surcharge as demand grew, clinker ran short and energy supply was cut, prompting a rapid policy reversal. Prices had roughly doubled at the time.
Competitors are also adding capacity. Huaxin Cement was completing an 800,000 tonne a year plant in Chegutu, due for commissioning in early 2026. It is also expanding at Mt Hampden, where it plans to triple output. According to a transcript of the earnings call, PPC management said the competing projects it knows of are grinding stations, not integrated plants. The transcript is unclear on this point and should be confirmed with PPC.
Power is a constraint. PPC said the 20 MW solar plant with batteries is a must-have in Zimbabwe because of frequent power dips, and should lift clinker output by 4 to 5 per cent.
Business Diary Analysis
The strategic logic is clear. Clinker is the most expensive and scarcest input in Zimbabwean cement. A producer that makes its own clinker is less exposed to import prices and to the supply shortages that have repeatedly disrupted construction. Higher volumes at its own plant are already lifting PPC’s margins. A second integrated plant would extend that advantage and could reduce the country’s reliance on imported clinker and cement.
The risks are equally clear. Cement is costly to move, so a plant must be close to both limestone and customers. Financing is unresolved, and Zimbabwe’s power supply, currency and policy environment remain uncertain. The reversal on import duties in 2025 shows how quickly the market rules can change. Competing capacity from Huaxin and others could also narrow the supply gap that makes the investment attractive.
For builders, developers and merchants, any easing of supply is a longer-term prospect. A 1.5Mt plant would take years to build and commission. In the meantime, prices will keep depending on kiln reliability, power and the import regime.
What’s Next?
Watch for a board decision, an announced EPC contract with Sinoma, confirmation of a site and limestone resource, and the financing structure. PPC’s results show it has the earnings to support an investment. They do not yet show it has committed to one.